A338 Collingbournes – Proposed Road Works 2nd-26th May 2017

The works are programmed to take place between Tuesday 2nd May 2017 and Friday 26th May 2017. Preliminary timings and working operations are listed below:

 1.       Phase 1: Thursday 4th May 2017, 19.00 to 00.00 hours;

Carriageway patching and associated works

 2.       Phase 2: Tuesday 2nd May 2017 to Friday 12th May 2017, 19.00 to 00.00 hours;

Full carriageway surfacing and associated works

 3.       Phase 3: Wednesday 3rd May 2017 to Thursday 4th May 2017, 19:00 to 06.00 hours;

Carriageway patching and associated works

 4.       Phase 4: Monday 15th May 2017 to Wednesday 24th May 2017, 19.00 to 00.00 hours;

Full carriageway surfacing and associated works

 5.       Phase 5: Wednesday 17th May 2017 to Wednesday 24th May 2017, 19.00 to 06.00 hours;

Carriageway patching and associated works

 6.       Various: Thursday 25th May 2017 to Friday 26th May 2017, 19.00 to 06.00 hours;

Remaining associated works – (road marking, ironwork adjustments, high friction surfacing)

 The phases referred to below are shown on the attached location plan & the temporary diversion route is shown on the attached Proposed Diversion plan.

1617SO0190-DR-D-0002 Location Plan (PDF – click to download/view)

1617SO0190-DR-D-0009 Proposed Diversion (PDF – click to download/view)

 On occasions there may be a slight delay in completion due to unforeseen circumstances such as late delivery of materials or weather interruptions.

 During the works period, access to enable residents to enter and egress from their property may temporarily be restricted due to site operations. The Contractor will endeavour to minimise the delay; although due to the nature of the works minor disruption is inevitable. It is essential that the road remains un-trafficked until the new material has set, as early trafficking could lead to premature failure. Dedicated Traffic Management operatives at the extent of the closures will monitor access and give motorists assistance.

Subject to programme, some additional weekend works may be required.

Regards,

Daniel Ward